By Bizodisha Bureau, Bhubaneswar, November 13, 2022: The Odisha government has sanctioned Rs 150 crore for speedy execution of the much-awaited Khurda Road-Bolangir rail line project with the Indian Railways commissioning the 10.5 km of newly-laid broad gauge line between Bichhupali and Jhartarbha.

Principal Secretary, Commerce and Transport Department, B P Sethi, has directed state government officials to release the fund to railways for early completion of the project.

The state government has given land free of cost and bearing 50 per cent construction cost for the 306.25 km Khurda Road-Bolangir railway project.

“I am directed to convey the sanction of the Governor to an expenditure of Rs 150 crore only for development of Khurda Road-Bolangir NBG Rail Link Project from 112 km 289 km during the year 2022-2023,” Transport Department Financial Advisor cum Special Secretary wrote to the Accountant General.

Recently, the state government held a high-level meeting with senior officials from Central government, Railway, Forest Department and Revenue Department to expedite the project. Decisions have also been taken to fast-track the forest clearance at the earliest in a time bound manner, the official said.

Though survey of the new rail line between Khurda and Bolangir, connecting the coastal region of the state with the western district, was done in 1945, it got sanction from the Centre only in 1994-95 and the project is already delayed by more than 20 years due to lack of funds following which the state government signed an MoU with railways to contribute certain amount of funds for expediting the works.

Meanwhile, sources said the ambitious project is also being delayed due to non-issue of Stage-I forest clearance. Of the total length of 306 km of the Khurda Road-Bolangir new railway project, 91 km from Khurda Road to Nuagaon has been commissioned. Now, another 10.5 km between Bichhupali and Jhartarbha is commissioned.

Officials said that the work is in progress from Nuagaon to Daspalla (91 km to 106 km) and target is set to commission it by March 2023. The work from Daspalla to Buguda (106 km to 121 km) is very slow due to non-issue of Stage-I forest clearance from the Ministry of Environment and Forest, the sources said.

Similarly, work from Buguda to Banigocghha is also yet to start due to non-issue of the Stage-I forest clearance. In total, the Government of India is yet to issue required forest clearance from 112 to 180 km while the work from 180 to 275 km is in progress and work at 275-301 km already commissioned.

Meanwhile, the East Coast Railways in a statement said that the Commissioner of Railway Safety (CRS) has inspected this newly laid Bichhupali and Jhartarbha line on November 10.

The CRS inspected the safety aspects of the newly rail line like railway track, signalling system, bridge works and others thoroughly and declared fit for the purpose for 10.65 km line of the on-going Khurda Road-Balangir Rail line project.

The railways have been constructing the line from both the sides, from Khurda Road and Bolangir, for early completion of the project.

Leave a Reply

Be the First to Comment!

avatar
  Subscribe  
Notify of