By Our Correspondent in Bhubaneswar, February 26, 2015 :

railway map odisha

Odisha has finally something to smile with Union Railway Minister, Suresh Prabhu showering largesse on the state by hiking budgetary allocation by 120% compared to the last year’s allocation of Rs 1420 crore in his maiden Railway Budget presented in the Lok Sabha on Thursday.

The state has received an allocation of Rs 3112.48 crore in the 2015-16 Railway Budget against its demand of Rs 3,200 crore.

Even chief minister Naveen Patnaik recognizes the higher budgetary allocation by the Railways to the state.

“I understand that there is an overall increase of about 53% in the Budget outlays of Railways. Odisha also has been correspondingly given an increase in the allotment. Further due allocations have been made for our ongoing major projects like Khurda-Bolangir, where the state government has committed to give land free of cost and bear 50% of the project cost. Some of the traditionally neglected railway sections like Sambalpur-Titlagarh, Sambalpur Talcher have been given due weightage,” Patnaik told reporters here.

RAILWAY BUDGET FOR ODISHA PROJECTS

SL NO. NAME OF PROJECT BUDGET ALLOTED (in crores)
01 ANGUL-SUKINDA New line, 98.7 KMs 75.00
02 Daitari-Bansapani New Line, 185 KMs 12.00
03 Haridaspur-Paradeep New Line, 82 KMs 36.8
04 Khurda Road-Bolangir, 289 KMs 195.00
05 Lanjigarh-Junagarh, 7.50
06 Talcher-Bimalagarh 280.00
07 Jharsuguda-Rengali Doubling 31.00
08 Sambalpur-Rengali Doubling 2.60
09 Khurda Road-Barang 3rd line 32.00
10 Cuttack-Barang 4.00
11 Sambalpur-Talcher Doubling 97.00
12 Delang-Puri Doubling 100.00
13 Sambalpur-Titilagarh Doubling 470.00
14 Raipur-Titilagarh 241.52
15 Bansapani-Jakhapura 513.00
16 Brundamal-Jharsugura Fly Over connection for joining down line 11.00
17 Barang-Rajathagarh Doubling 16.00
18 Bhadrak-Nirgundih 3rd Line 125.00
Total 2249.42
NEW WORKS
01 Vizianagaram-Samalpur 58.31
02 Jharapada-Budhapank 3rd& 4th line 45.73
03 Budhapank-Salegaon 3rd& 4th Line 34.30
04 Bhadrak-Vizianagaram 3rd line 120.05
05 Koraput-Singapur Road 37.50
06 Khurda-Vizianagaram Bye Pass 2.29
Total 298.18
Grand Total 2548.22
(A) Total Plan Outlay of ECoR 1576.01
 (B) Extra Budget Resources 1536.47
Total Plan Outlay inclusive EBR (A+B) for ECoR 3112.48

The Budgetary allocations for construction of new rail lines are Khurda Road-Bolangir (Rs 195 crore), Angul-Duburi-Sukinda Road (Rs 75 crore), Haridaspur-Paradip (Rs 36.8 crore), Talcher-Bimalagarh (Rs 280 crore). However, other new railway link projects like Kendujhar-Badamapahar, Jeypore-Nabrangpur, Puri-Konark and Lanjigarh-Junagarh have been deprived of allocations.

For doubling and third line project, the Railways ministry have allotted Rs 1,527.8 crore and funds have been allocated for crucial projects like Banspan-Daitari-Jakhapura (Rs 513 crore), Samblapur-Titlagarh (Rs 470 crore), Sambalpur-Talcher (Rs 194 crore), Bhadrak-Nirgundi third line (Rs 125 crore) and Delang-Puri (Rs 100 crore).

Electrification projects have been allocated Rs 293.38 crore. The Budget has set aside Rs 137.88 crore for Vizianagram-Rayagada-Titlagarh-Raipur project, Rs 100 crore for Jharsuguda-Sambalpur-Titlagarh and Rs 55 crore for Sambalpur-Angul electrification projects.